INITIATION

OBJECTIVES

  • Establish Goals and Objectives
  • Launch Project Website
  • Establish a Planning Advisory Committee (PAC)

MEETINGS

  • PAC Meeting #1 (October, 23, 2024)
  • Public Information Workshop #1

PHASE ONE

OBJECTIVES

  • Inventory of Existing Conditions
  • Aviation Forecasts
  • Draft Phase One Working Papers

MEETINGS

  • PAC Meeting #2 (March 4, 2025)
  • Public Information Workshop #2

PHASE TWO

OBJECTIVES

  • Demand/Capacity and Facility Requirements
  • Alternatives Analysis
  • Safety Risk Management
  • Draft Phase Two Working Papers

MEETINGS

  • PAC Meeting #3 (August 5, 2025)
  • Public Information Workshop #3

PHASE THREE

OBJECTIVES

  • Recommended Development Concept
  • Environmental Inventory and Overview
  • Capital Improvement Program
  • Airport Layout Plan Drawings
  • Draft Phase Three Working Papers

MEETINGS

  • PAC Meeting #4 (October 29, 2025)
  • Public Information Workshop #4

FINALIZATION

(TBD)

OBJECTIVES

  • Draft Final Master Plan Report
  • Deliver Digital and Printed Copies of Finalized Report

MEETINGS

  • ALP approval by Federal Aviation Administration (FAA)
  • Local Approval of ALP